Inventory & Safety Stock Calculator
Balance ordering cost, carrying cost and the buffer against uncertain demand.
Single item · continuous review · cycle service target
Start with the example, then replace every assumption with your own. All monetary amounts are in USD.
How the model works
Annual holding cost per unit H = unit cost × carrying rate. Economic order quantity EOQ = √(2 × annual demand × order cost ÷ H). The practical quantity evaluates the pack multiples immediately below and above EOQ, moving either up to the minimum feasible pack multiple if required. It selects the lower ordering-plus-cycle-stock holding cost; it does not simply round EOQ upward.
Average daily demand = annual demand ÷ demand days. Standard deviation of lead-time demand = √(mean lead days × daily demand variance + average daily demand² × lead-time variance). Unrounded safety stock = normal z-score for the cycle service target × lead-time demand standard deviation. Reorder point = expected lead-time demand + unrounded safety stock, rounded upward once to a whole unit. Displayed safety stock is the effective buffer after that rounding: reorder point minus expected lead-time demand. It can be fractional because average demand can be fractional.
Reorder when inventory position (on hand + on order − backorders) reaches the reorder point. Relevant annual policy cost = ordering cost + holding cost of average cycle stock and safety stock. Purchase cost is shown separately because it does not vary with order quantity in this model.
Assumptions and limitations
Assumes steady average demand, independent daily demand, independent demand and lead time, a normal approximation, instantaneous replenishment when the order arrives, constant prices/costs and no shortages in the basic EOQ economics. Variable lead-time formula is a random-sum approximation; highly skewed, correlated, intermittent or seasonal demand needs simulation or a fitted model.
Cycle service is not the fraction of units filled. Safety stock is not a guarantee. No quantity discounts, shelf life, warehouse capacity, service penalties or multiple-item constraints. Orders/year and days between orders are long-run averages. Zero annual demand requires zero daily-demand variability and suppresses replenishment estimates; review dormant stock separately. Current-order cost uses the same safety stock so the comparison isolates order size. If the current quantity violates the entered pack or minimum-order rules, its cost is shown only as a historical comparison. Average inventory and holding cost use the standard cycle-stock-plus-buffer approximation; they are not a simulation of shortages.
Method references
- MIT OpenCourseWare: EOQ and inventory-cost sensitivity
- MIT OpenCourseWare: probabilistic demand and safety stock
- APICS: safety stock, lead-time variation and cycle service level
References explain the methodology. Example inputs are illustrations, not market quotes or benchmarks.
Planning estimate only, not a valuation opinion, accounting conclusion or investment recommendation. Validate assumptions with your records and appropriate advisers. Calculations use unrounded values; displayed amounts may differ slightly due to rounding. Calculations run in your browser. Avoid entering confidential information.